Amendment of EIA Notification 2006 for Change in product mix…

 “The new projects or activities or the expansion or modernization of existing projects or activities listed in the Schedule to the EIA notification entailing capacity addition with change in process or technology and/or product mix shall be undertaken in any part of India only after obtaining prior environmental clearance from the Central Government or as the case may be, by the State Level Environment Impact Assessment Authority”

 This Notification said that,

1.      In paragraph 2, for clauses (ii) and (iii), the following clause shall be substituted, namely:-

 “(ii) Expansion, modernization or any change in the product mix or raw material mix in existing projects or activities, listed in the Schedule to this notification, resulting in capacity beyond the threshold limits specified for the concerned sector in the said Schedule, subject to conditions and procedure provided in the sub-paragraph (ii) of paragraph 7”;

2.      In paragraph 7,-

 A.    in the heading, the words “for New Projects” shall be omitted; 

B.     in the sub-paragraph (i), the words “For new projects or activities listed in the Schedule to this notification:” shall be inserted as heading to the sub-paragraph;

C.    in the sub-paragraph (ii),- (I) in the clause (a), after the words “application shall be appraised accordingly for grant of environmental clearance”, the following words shall be inserted, namely:- “in respect of projects or activities other than falling in clause (b) and (c)”;

(II) for clauses (b) and (c), the following clauses shall be substituted, namely:-

‘(b) Existing projects (having Prior Environmental Clearance) with no increase in pollution load: Any increase in production capacity in respect of processing or production or manufacturing sectors (listed against item numbers 2,3, 4 and 5 in the Schedule to this notification) with or without any change in (i) raw material-mix or (ii) product-mix or (ii) quantities within products or (ii) number of products including new products falling in the same category or (iv) configuration of the plant or process or operations in existing area or in areas contiguous to the existing area (for which prior environmental clearance has been granted) shall be exempt from the requirement of Prior Environmental Clearance provided that there is no increase in pollution load (derived on the basis of such Prior Environmental Clearance):

Provided that such exemption shall be applicable only consequent to –

A.    The project proponent furnishing information regarding such changes along with no increase in pollution load certificate, from the environmental auditor or reputed institutions empanelled by the State Pollution Control Board or Union Territory Pollution Control Committee or Central Pollution Control Board or Ministry of Environment, Forest and Climate Change, as per the procedure laid down in Appendix-XIII, on PARIVESH portal as well as to the concerned State Pollution Control Board or Union Territory Pollution Control Committee.

Note: If on verification, the State Pollution Control Board or Union Territory Pollution Control Committee, as the case may be, after giving the project proponent the opportunity of being heard, holds that such change or expansion or modernization results in increase in pollution load, the exemption claimed under this clause shall not be valid and it shall be deemed that the project proponent was always liable to obtain prior environmental clearance, in respect of such change or expansion or modernization, as per the clause (a) and the provisions of Environment (Protection) Act, 1986 shall apply accordingly;

B.   Installation and implementation of Online Continuous Monitoring System (OCMS) with at least 95% uptime, connected to the servers of the Central Pollution Control Board and State Pollution Control Board or Union Territory Pollution Control Committee concerned to report the quantity and quality, of emission and discharges:

Provided further that the provisions of this clause shall not be applicable if such change or increase results in change in category of project or activity from Category-‘B2’ to either Category-‘A’ or Category ‘B1’

(c) Any change in configuration of the plant or activity from the environmental clearance conditions during execution of the project after detailed engineering, in respect of projects or activities, falling in any item of the Schedule to this notification, shall not require prior environmental clearance, if there is no change in production capacity and there is no increase in pollution load subject to furnishing particulars of such changes on PARIVESH portal in the format as may be provided by the Government from time to time, before implementing such changes whereupon a system generated acknowledgement will be issued by the concerned Regulatory Authority.

Explanation:- For the purpose of this sub-paragraph, “Pollution load” shall be determined on the basis of multiplication of quantity and concentration of different components and parameters (as provided or referred in the Prior Environment Clearance or the Environment Impact Assessment Report (EIA) and Environment Management Plan based on which such Prior Environment Clearance has been granted), in respect of emissions, effluents or discharge, solid, industrial hazardous waste and such other parameters notified under the Environment (Protection) Rules, 1986 as amended from time to time.’

3.     In the Schedule, against item 5(g), after the entry in column (5), the following entry shall be inserted, namely:-

“Note: Expansion of sugar manufacturing units or distilleries, having Prior Environment Clearance and for production of ethanol, to be used as fuel for blending only as certified by the competent authority, shall be appraised as Category “B2” projects.”;


For Appendix-XIII, the following Appendix shall be substituted, namely:-

 “Appendix-XIII

Verification of No Increase in Pollution Load

 The instant amendment in EIA Notification exempts the requirement of Prior Environmental Clearance for any increase in production capacity in respect of processing or production or manufacturing sectors (listed against item numbers 2,3, 4 and 5 in the Schedule to this notification) with or without any change in (i) raw material-mix or (ii) product-mix or (ii) quantities within products or (ii) number of products including new products falling in the same category or (iv) configuration of the plant or process or operations in existing area or in areas contiguous to the existing area specified in the environmental clearance of the project. This facility is available to those units which have obtained prior environmental clearance under EIA Notification, 1994 and EIA Notification, 2006. To claim exemption from obtaining Prior Environment Clearance in respect of such cases, the project proponent shall follow the following process:-

 1.      The project proponent is required to obtain a certificate of „no increase in the pollution load‟ from the environmental auditors or reputed institutions, to be empanelled by the State Pollution Control Board or Central Pollution Control Board or Ministry of Environment, Forest and Climate Change (hereinafter referred to as the Ministry).

2.      A copy of “no increase in pollution load” certificate and intimation, as provided by the Ministry from time to time on PARIVESH portal, shall be uploaded by the unit for which system generated acknowledgement shall be issued online;

.     The unit shall inform the State Pollution Control Board or Union Territory Pollution Control Committee, as the case may be, in specified format along with-

 i.     “no increase in pollution load” certificate from the Environmental Auditor or reputed institutions empanelled by the State Pollution Control Board or Pollution Control Committee or Central Pollution Control Board
or Ministry;

ii.      Last Consent to Operate certificate for the project or activity; and

iii.   online system generated acknowledgement of uploading of intimation and „no increase in pollution load‟ certificate on PARIVESH Portal;

4.      The information so received shall be examined by the State Pollution Control Board or Union Territory Pollution Control Committee, as the case may be, who shall take decision on such information, received from the project proponent.

.     If on verification the State Pollution Control Board or Union Territory Pollution Control Committee, as the case may be, holds that the change or expansion or modernization will result or has resulted in increase in pollution load, the exemption claimed under this clause shall not be valid and it shall be deemed that the project proponent was liable to obtain Prior Environmental Clearance before under taking such changes or increase, as per the clause (a) of sub-paragraph (ii) of paragraph 7 of this notification and the provisions of Environment (Protection)
Act, 1986 shall apply accordingly.

 Note: For removal of doubts, it is clarified that it shall be the responsibility of the project proponent to satisfy itself about “no increase in pollution load” as a result of changes, expansion or modernization, as the case may be, before under taking such changes or increase, and the project proponent shall be liable for action under the provisions of the Environment (Protection) Act, 1986 if on verification of facts or claim it is found that such change or expansion or modernization involves increase in pollution load.”.